Since manufacturing an outdoor and large-sized billboard
takes a lot of time, the working time required may be directly affected by
weather changes, such as winds and rain. Moreover, without accurate planning,
unforeseen situations may occur and even cause work delays. This report reviewed
how to enhance work efficiency including fabrication and installation process of
the billboard
Considering Working Environment Jaesung General hospital requested
World Housing, the manufacturer of rooftop billboards to manufacture and install
its rooftop billboard. World Housing president, Hwang In-beom, said that the
hospital did not want to disturb the patients, and we planned to pre-fabricate
and assemble all components as many as possible on our companies, and had to
bring them to the hospital. Since there was no other choice but to use a crane
in lifting all materials required for the project to the worksite of the
hospital's eight-floor housetop, the manufacturer assembled the reflective
display, frame, and other components as lightweight as possible so that they
could be lifted by a crane. After the completion of assembling them, the company
transported all components to the worksite. It took a whole day to convey those
components, while it took only about two hours to lift eight tons of assembled
components from the ground to the housetop of the hospital. The H-beam frame was
lifted by the housetop tower elevator for the H-beam work before other
components were arranged appropriately on the housetop.
Lifting by a Crane For Working Efficiency The company initially
planned to install the rooftop billboard by a crane after fabricating
large-format digital graphics and assembling all components lifted on the
rooftop of the hospital. The company, however, could not find out a crane that
was capable of lifting the eight-ton structure, and thus, assembled a structural
frame that could be supported by a 25-ton crane. A 100-ton crane was considered,
but a 50-ton crane was finally regarded cost effective. Mr. Hwang of World
Housing explained, “Each structure could be moved by men. Unlike assembly work,
though, a lift by a crane was more beneficial in terms of cost and time
savings." It was important to determine which installation process were the most
efficient in terms of cost and timesavings. Likewise, one should make an
accurate calculation on equipments for reducing work time, thus reducing labor
costs, and, consequently, total work costs. It was more critical, though, to
accurately identify manpower, equipment, structural obstructions such as
surrounding buildings and electric poles, road traffic situations, and climate
changes like rainfall and strong winds, during the planning stage.
The Safety is most critical Considering the nature of the
location where housetop billboards were installed, outdoor billboards should be
more stably and firmly installed than the other outdoor advertisements. They
should be able to withstand even typhoons. Large-scale housetop billboards could
lead to secondary disasters. Thus, Sign codes require billboards to be
structurally safe to withstand winds of over 34 m/s. To guarantee such
structural safety, billboards require reinforcement-oriented designs and
installations. Chemical anchor technology used in manufacturing sub-structural
H-beams could enhance the strength of adhesives, thus withstanding massive
loads. Also, adhesives could enhance the concrete's chemical safety and lower
water absorption. Due to its strengths, chemical anchor technology is used not
only in ordinary construction, but also in underwater construction. The
construction presented here used bolts in all joints. Major areas were joined by
bolts, and then welded. The working area where bolts could not be used were all
welded. Such bolts working make the project boost efficiency and helped shorten
the installation time. Woo Sun-hun, president of Sunbong Planning, which also
worked with the project, explained, "With bolts, oxygen canisters are no longer
necessary, thus boosting efficiency. It is difficult for workers to conduct
welding on the construction site at a time, but other workers can do bolt work
at a time."
|